Wave energy converter installation in Heraklion: First preparation phase successfully completed
This summer SINN Power will install five wave energy converter (WEC) modules with the revised SINN Power technology in Greece. After four weeks of construction, the preparations for the installation of the first two modules on the port wall were completed today.
(firmenpresse) - The two WEC modules, which are funded by the German Federal Government, primarily serve to test the updated technology for its functionality. If everything goes as planned, the revised modules will already be produc-ing electricity within a few weeks. With the successful construction of the supporting structure, the key prerequisites for the fol-lowing steps are now given.
In the construction phase, which is divided into three parts, first the supporting structure will be attached to the port wall. Then the modules are set up. Finally, the modules are lifted with a crane over the wall and mount-ed on the supporting structure. From this point on they can be put into operation.
In spring of 2018 the production of the indi-vidual components, which took place mostly in Germany, was completed. Since the WEC modules are designed to be transported as easy and quick as other goods to any loca-tion in the world in a single ISO container, they could then be easily transported to Greece by truck.
After the arrival of the truck with the compo-nents in early May, the SINN Power engi-neering team began welding the supporting structure as a connection between the port wall and the WEC module.
In the past week it was attached to the breakwater wall with a crane. This now forms the basis for the installation of the module. The lifting rods, generators and floating bodies will be assembled in the coming weeks. The installation and commis-sioning of the first two WEC modules is scheduled for early July.
By 2019, three more WEC test modules are to be built on the port wall of Heraklion in Crete. They will test the electrical connection of several generators in practice and thus serve the further development of the innova-tive wave energy technology.
The project is permanently supervised by five to seven SINN Power engineers at the project location in Greece. They monitor the mechanical loads of the revised WEC mod-ules and evaluate the data on the generated electricity.
After a two-year development period, the team expects the new module concepts to significantly increase performance, com-pared to the first generation of WEC mod-ules built in 2015.
Images and text are free to use,
higher resolution is available on request.
Press contact:
Carla Knappik
Corporate Communications Assistant
carla.knappik(at)sinnpower.com
+49 (0)89 9256 6192
SINN Power GmbH
Germeringer Str. 9, 82131 Gauting, Germany
www.sinnpower.com
View the press release here: https://www.sinnpower.com/single-post/2018/06/11/Wave-energy-converter-installation-in-Heraklion-First-preparation-phase-successfully-completed
Sehen Sie die Pressemitteilung hier ein: https://www.sinnpower.com/single-post/2018/06/12/Wellenkraftmodul-Installation-in-Heraklion-Vorbereitungen-erfolgreich-abgeschlossen
Themen in dieser Pressemitteilung:
Unternehmensinformation / Kurzprofil:
SINN Power''s floating wave energy converter supplies people on coasts all over the world with cost-efficient, reliable and easy-to-install renewable electricity from ocean waves. www.sinnpower.com
Carla Knappik
Corporate Communications Assistant
carla.knappik(at)sinnpower.com
+49 (0)89 9256 6192
Images and text are free to use,
higher resolution is available on request.
Press contact:
Carla Knappik
Corporate Communications Assistant
carla.knappik(at)sinnpower.com
+49 (0)89 9256 6192
SINN Power GmbH
Germeringer Str. 9, 82131 Gauting, Germany
www.sinnpower.com
Datum: 11.06.2018 - 18:26 Uhr
Sprache: Deutsch
News-ID 1537106
Anzahl Zeichen: 3272
contact information:
Contact person: Carla Knappik
Town:
Gauting
Phone: +498992566192
Kategorie:
Environment
Typ of Press Release: Erfolgsprojekt
type of sending: Veröffentlichung
Date of sending: 12.06.2018
Anmerkungen:
Diese Pressemitteilung wurde bisher 1326 mal aufgerufen.
Die Pressemitteilung mit dem Titel:
"Wave energy converter installation in Heraklion: First preparation phase successfully completed
"
steht unter der journalistisch-redaktionellen Verantwortung von
SINN Power GmbH (Nachricht senden)
Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).