businesspress24.com - Feasibility Study Confirms Cardinal´s Namdini as a Tier One Gold Project
 

Feasibility Study Confirms Cardinal´s Namdini as a Tier One Gold Project

ID: 1553425

(firmenpresse) - 5.1 Moz Ore Reserve* and a 15 Year Mine Life with early payback
Cardinal Resources Limited (ASX / TSX : CDV) (Cardinal or the Company) https://www.commodity-tv.net/c/search_adv/?v=299176 is pleased to announce the results of the Feasibility Study (FS) for the Namdini Gold Project (Namdini or the Project) in Ghana, West Africa. The FS confirms Namdini as a gold project with attractive economic returns.

HIGHLIGHTS
- 5.1 million ounces (Moz) Ore Reserve* (Pre-Feasibility Studyw (PFS) 4.76 Moz)
- 421,000 oz in first 12 months (PFS 420,000 oz); 1.1 Moz forecast for first 3 years of full production
- US$1.46 billion in undiscounted, pre-tax free cashflow forecast with the current life of mine (LOM) plan of 15 years at US$1,350/oz (US$2.05 billion undiscounted, pre-tax free cashflow at US$1,500/oz)
- US$324 million in undiscounted, pre-tax free cashflow, forecast during 1st Year of full production at US$1,350/oz (US$384 million first year pre-tax free cashflow at US$1,500/oz)
- US$348 million capital expenditure (CAPEX) plus US$42 million contingency allowed with a robust level of accuracy of +15/-5% (PFS US$414 million total Capex; +30/-20% accuracy)
- CAPEX payback of 21 months at US$1,350/oz (12 months at USD$1,500/oz); driven by early higher grades and recoveries, low strip ratio and low costs, within the starter pit
- Low all-in sustaining costs (AISC) of US$585 during CAPEX payback (PFS US$599)
- Pit design LOM Strip Ratio 1.9:1 (PFS 1.4:1); Starter pit Strip Ratio of 0.9:1; LOM pit design based on US$1,235/oz (PFS US$1,105/oz)
- Financial Model based on US$1,350/oz for 15 years (PFS US$1,250/oz)
- 4.2 Moz (130 metric tonnes) produced over 15 years (PFS 3.9 Moz); AISC US$895/oz (PFS US$769/oz)
- Aachen Process Technology has been adopted to provide economic benefits via operating cost savings; 85% gold recovery during first three years; 83% gold recovery for current LOM plan
- Namdini 9.5 Mtpa gold project is based upon a single, large open-pit with a conventional process plant design; crush, grind, float, regrind, high shear oxidation (AachenTM) and carbon in leach (CIL)




- First gold pour targeted for H2 2022 (subject to financing in H1 2020)
- Namdini Project Net Present Value (NPV) and Internal Rate of Return (IRR) at US$1,350/oz:
- - Net Present - Internal Rate of
Value Return
(NPV (IRR)
5)
- Pre-tax - US$914 Million - 43.0%
- Post-tax- US$590 Million - 33.2%

- Cardinals Board has approved this Feasibility Study and plans to further de-risk the project by commencing the Front End Engineering Design (FEED) programme and further enhancement of the Project Execution Plan (PEP). Early site works and advancement of engineering towards construction, will be funded through Cardinals strong cash position of circa A$27 million.
* 138.6 Mt (at) 1.13 g/t Au; 0.5 g/t cut-off, inclusive of 0.4Moz Proved (7.4 Mt (at) 1.31 g/t Au) and 4.7Moz Probable (131.2 Mt (at) 1.12 g/t Au); 0.5 g/t Au cut-off.
w Pre-Feasibility Study (PFS) released on ASX / TSX 18th September 2018
129.6 Mt (at) 1.14 g/t Au; 0.5 g/t cut-off, inclusive of 4.76 Moz Probable (129.6 Mt (at) 1.14 g/t Au); 0.5 g/t Au cut-off.

Project Sensitivity Analysis
Sensitivity to US$ Gold Price; Pre and Post-Tax
https://www.irw-press.at/prcom/images/messages/2019/49247/28 Oct 2019 FS Confirms Namdini as a Tier One Gold Project_Kurz.001.png


Capital Cost Estimate
The following Table compares the major Project parameters for the FS with those for the PFS:
Direct FS ($US Million) PFS ($US Million)
+15/-5% accuracy +30/-20% accuracy
Process Plant 230 205
Infrastructure & 57 76
Utilities

Sub-total direct 287 281
Indirect FS ($US Million) PFS ($US Million)
Engineering & 36 37
Contractors

Owners costs 25 35
Sub-total indirect 61 72
Contingency 42 61
Total Capital Cost 390 414

Sensitivity of Project Outcomes to US$ Gold Price; Pre-Tax

https://www.irw-press.at/prcom/images/messages/2019/49247/28 Oct 2019 FS Confirms Namdini as a Tier One Gold Project_Kurz.002.png

Sensitivity of Project Outcomes to US$ Gold Price; Post-Tax
https://www.irw-press.at/prcom/images/messages/2019/49247/28 Oct 2019 FS Confirms Namdini as a Tier One Gold Project_Kurz.003.png

US Dollar Gold Price Sensitives
The FS has been evaluated at a gold price of USD$1,350 per ounce. The average US$ gold price per gold ounce for the period from October 2017 to current day was US$1,387 per ounce. During the period, the US dollar gold price has been in steady uptrend from a low of US$1,177 in August 2018 to a high of US$1,550 per ounce traded during September 2019.

Key Technical and Financial Outcomes
The key technical and financial outcomes from the FS on a 100% basis are summarised in the following tables. Further details are provided in the Appendix to this announcement.

Financial Summary for 9.5 Mtpa throughput (based upon a gold price of US$1,350/oz)
KEY ECONOMIC RESULTS UNIT FEASIBILITY
STUDY

Capital cost (including 11% US$ M 390
contingency)

All-in Sustaining Starter US$/oz 585
Cost Pit US$/oz

(AISC)1
Life of 895
Mine

Total Project payback Months 21
Pre-Tax NPV US$ (5% discount US$ M 914
rate)

Post-Tax NPV US$ (5% discount US$ M 590
rate)

Pre-Tax IRR % 43
Post-Tax IRR % 33
Table Notes:
1 Cash Costs + Royalties + Levies + Life of Mine Sustaining Capital Costs (World Gold Council Standard)
Royalties calculated at a rate of 5.5% and a corporate tax rate of 32.5%; both subject to negotiation, and expected to be finalised over coming months.

Starter Pit Production Summary
KEY ESTIMATED PRODUCTION UNIT FEASIBILITY STUDY
RESULTS

Gold price US$/oz 1,350
Gold produced (average for f(koz/yr) 361
ull production
years)

Gold head grade (Starter Pitg/t Au 1.41
, Ore
Reserve
)
Gold recovery (Starter Pit) % 85
Strip ratio (Starter Pit) W:O 0.9 :1
Ore mined (0.5 g/t cut-off Tonnes (Mt) 47
grade)

Waste mined Tonnes (Mt) 43
Starter Pit life (including Months 27
ramp-up)

Total Project payback Months 21

LOM Production Summary (including Starter Pit)
KEY ESTIMATED PRODUCTION UNIT FEASIBILITY
RESULTS STUDY

Gold price US$/oz 1,350
Gold produced (average for LO(koz/yr) 287
M

full production years)
Gold produced (LOM) (Moz) 4.2
Gold head grade (LOM, Ore g/t Au 1.13
Reserve
)
Gold recovery (LOM) % 83
Strip ratio (LOM) W:O 1.9 : 1
Ore mined (0.5 g/t cut-off Tonnes (Mt) 138.6
grade)

Waste mined Tonnes (Mt) 263
Mine life (Including ramp-up years 15
and mine
closure)

Capital cost (including 11% US$ M 390
contingency)

Total Project payback Months 21

Production Profile and LOM AISC

https://www.irw-press.at/prcom/images/messages/2019/49247/28 Oct 2019 FS Confirms Namdini as a Tier One Gold Project_Kurz.004.png


Ongoing Activity
The activities summarised in the Project development schedule below are subject to favourable timelines for finalising project funding, permitting, contracting and procurement.

Further Project optimisation and regional exploration
In conjunction with moving the Project toward a financial investment decision, work continues on further project optimisation and regional exploration utilising Cardinals strong cash at bank of approximately A$27 million.

Cardinals ~900 km2 of prospective exploration tenure within hauling distance of the proposed Namdini gold production plant remains a short-term opportunity for project enhancement.

Exploration activities, including drilling, will recommence shortly with the stated aim of identifying shallow, high grade deposits that can augment existing Namdini ore to further enhance the current project economics. Recent positive results from exploration activities, for example at Ndongo East Refer to the announcements Cardinal Intercepts HighGrade Shallow Gold at Ndongo East released to the ASX and TSX on 27 March 2019 and Cardinal Reports Further Shallow HighGrade Gold at Ndongo East released to the ASX and TSX on 10 July 2019.
, provide encouragement that higher grade gold systems may exist in the region within trucking distance to the Namdini deposit.

Funding and Strategic Alternatives
Cardinals Board has approved this Feasibility Study and recommends progressing the Project to construction pending successful completion of financing activities.

The Company has been actively working with its appointed debt advisor, Cutfield Freeman & Co (London) to secure Project debt finance on competitive terms and continues to assess various funding options.
In early 2019, the Company commenced Project finance discussions with a number of Australian and International Banking groups from which the Company received a number of preliminary (nonbinding) financing term sheets. Discussions with these interested financial institutions have progressed where financial and technical due diligence has commenced, with a data room prepared and accessed, with several technical site visits already conducted. Review of financing options for the Namdini Project will be completed in due course following the Feasibility Study.

In addition to traditional financing solutions, the Company is concurrently evaluating strategic alternatives to bring the project into production with a view to maximising economic outcomes for Cardinal shareholders.
A final financing decision will be made at a time assessed as most appropriate and beneficial to the Company.
In the meantime, the Company remains in a strong financial position with cash reserves of approximately A$27 million.

Opportunities
The FS demonstrates a viable, globally significant, long-life gold project at Namdini. Potential remains for further improvements in Project economics which will form the basis of ongoing evaluation work, including:
- FEED and PEP programmes incorporating Whittle Consultings mine and schedule optimisation plan.
- OPEX savings by evaluating a flotation cleaner circuit; potential to reduce required regrind power.
- Additional Mineral Resources that are not part of the current Ore Reserve which represent lateral strike and depth extensions to the current LOM pit design at US$1,235/oz. Subject to the outcome of additional drilling beyond the current pit design, any economic discovery not in the current mine plan may extend the life of the current mine plan which may also include a new underground mine plan.
- The Regional land package may also have potential to define satellite pits with close proximity to Namdini. Recent results from drilling completed within the Ndongo Project, located approximately 24 km north of Namdini are within hauling distance. Refer to the announcements Cardinal Intercepts HighGrade Shallow Gold at Ndongo East released to the ASX and TSX on the 27 March 2019 and Cardinal Reports Further Shallow HighGrade Gold at Ndongo East released to the ASX and TSX on the 10 July 2019
Drill testing new zones of high-grade gold mineralisation to define satellite pits will recommence soon.

Archie Koimtsidis, Managing Director and Chief Executive Officer, commented:
Cardinals Technical Team, led by our Chief Operating Officer Dave Anthony, along with Lycopodium, Golders and various study managers, have delivered a compelling and robust technical and economic outcome, paving the way for our planned development of the Namdini Gold Project.

With over 1 million ounces slated for production in the first three years; 421,000 oz in Year 1 alone, and an average annual gold production of 287,000 oz over a 15-year mine life, Namdini ranks amongst the worlds largest known, financially robust, undeveloped gold projects.

Namdini has a 5.1 Moz Ore Reserve that is projected to generate US$1.46 billion in undiscounted, pre-tax free cashflow over 15 years including US$324 million in undiscounted, pre-tax free cashflow during its 1st Year of full production, based on a gold price of US$1,350, which is significantly below the current spot gold price.

Since the discovery of Namdini in 2015, we have continued to be focused on de-risking the project and have reached a robust Project CAPEX accuracy level of +15/-5% for this Feasibility Study. Unlike whole of ore gold processing plants, we have the benefit of being able to produce a concentrate for gold extraction on site which means that we have a much smaller back half of the plant providing a huge positive impact on capital costs. Economic and technical optimisation confirms a large, single open-pit utilising a conventional process plant with a throughput of 9.5 Mtpa and a very attractive 24-month debt payback.

On a social level, Namdini is poised to become the first large scale operating mine in the Upper East Region of Ghana, delivering sustainable prosperity and opportunities to all stakeholders. We are grateful for the continued overwhelming support of these communities and their elders along with the Government of Ghana to bring this project into production.

About Cardinal
Cardinal Resources Limited (ASX/TSX: CDV) is a West African goldfocused exploration and development Company which holds interests in tenements within Ghana, West Africa.

The Company is focused on the development of the flagship Namdini Gold Project.

Exploration programmes are also progressing at the Companys Bolgatanga (Northern Ghana) and Subranum (Southern Ghana) Projects.

To view the complete original news release in English, please follow the link:https://www.asx.com.au/asxpdf/20191028/pdf/449xz8p6mrm330.pdf

For further information contact:

Archie Koimtsidis -Alec Rowlands
CEO / MD-IR / Corp Dev
Cardinal Resources Limited -Cardinal Resources Limited
P: +61 8 6558 0573-P: +1 647 256 1922

Cannings Purple
Andrew Rowell or Peta Baldwin-
E: arowell(at)canningspurple.com.au
E: pbaldwin(at)canningspurple.com.au

In Europe:
Swiss Resource Capital AG
Jochen Staiger
info(at)resource-capital.ch
www.resource-capital.ch



Weitere Infos zu dieser Pressemeldung:

Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:





PresseKontakt / Agentur:



Bereitgestellt von Benutzer: irw
Datum: 28.10.2019 - 08:43 Uhr
Sprache: Deutsch
News-ID 1553425
Anzahl Zeichen: 3058

contact information:
Contact person:
Town:

Wien


Phone:

Kategorie:

Business News


Typ of Press Release:
type of sending:
Date of sending:
Anmerkungen:


Diese Pressemitteilung wurde bisher 445 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Feasibility Study Confirms Cardinal´s Namdini as a Tier One Gold Project

"
steht unter der journalistisch-redaktionellen Verantwortung von

Cardinal Resources Limited (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Cardinal Resources Limited



 

Who is online

All members: 10 568
Register today: 0
Register yesterday: 0
Members online: 0
Guests online: 77


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.