Lean projects are three times more likely to complete ahead of schedule according to Dodge Data & Analytics'' research

ID: 1477156

(firmenpresse) - ARLINGTON, VA -- (Marketwired) -- 12/21/16 -- Dodge Data & Analytics recently benchmarked the current state of capital project delivery performance and found a statistically significant correlation between use of Lean methods and better project outcomes.

To establish a benchmark, eighty-one owners responded to Dodge Data & Analytics'' survey by answering questions about their perceived best project and a typical project in the last three years -- providing data on schedule, budget, quality and safety performance as well as information on how the project team was organized, the commercial terms for the project and the management methods used.

On schedule and cost performance, which owners cite as most valuable, Dodge found that 24% of best projects finished ahead of schedule compared to only 6% of typical projects, and 46% of best projects finished under budget compared to only 10% of typical projects. A staggering 61% of typical projects finished behind schedule and 49% of typical projects completed over budget.

Why did some projects excel? Dodge studied the differences between best and typical projects, finding that best projects outperformed typical projects by doing the following three things:

Best projects had a higher usage of specific Lean management methods than typical projects. When looking deeper into the best of the best projects, researchers found that high Lean intensity projects (projects using a number of Lean management methods) are

"The research conclusions reached by Dodge Data & Analytics show strong correlations between added value for the owner and use of Lean methodologies, particularly where a number of Lean techniques are used in combination," said Dan Heinemeier, Executive Director of the Lean Construction Institute (LCI), the non-profit organization that sponsored the research.

Dodge found that 76% of best projects engaged key stakeholders before or during conceptualization, giving them the advantage over the 42% of typical projects that did not engage key stakeholders until design development or later. Key stakeholders represent, at a minimum, the owner, architect, MEP and structural engineers, construction manager/ general contractor and key trade contractors.





: Dodge found that best projects used more collaborative delivery methods and contract types than typical projects. Most best projects used Construction Management at Risk with Guaranteed Maximum Price, while most typical projects used Lump Sum Design-Bid-Build. Use of Integrated Project Delivery (IPD) and Shared Risk & Reward was used by approximately 20% of best projects.

For more information about the research and how to advance your own Lean journey, visit to watch Bevan Mace of Balfour Beatty Construction US talk more about the Dodge Data & Analytics study. You will also find a fact sheet that offers visual graphs and charts to better illustrate the research findings.

Questions about the research findings may be directed to Dan Heinemeier at .

Founded in 1997, LCI is a non-profit, membership-based organization with a vision to transform the built environment through Lean implementation. With common language, fundamental principles and basic practices, LCI aims to increase stakeholder satisfaction and project delivery value. The design and construction industry''s productivity level has remained nearly stagnant in 50 years as other industry''s thrive, but LCI sets out to improve the industry by facilitating continuous education through their Transforming Design and Construction book series, Lean instructional training courses and the annual LCI Congress and Design Forum. LCI advocates for using a variety of tools and techniques that help promote collaborative planning, waste elimination and work-site safety. For more information, please visit .

Dodge Data & Analytics is a technology-driven construction project data, analytics and insights provider. Dodge provides trusted market intelligence that helps construction professionals grow their business, and is redefining and recreating the business tools and processes on which the industry relies. Dodge is creating an integrated platform that unifies and simplifies the design, bid and build process, bringing data on people, projects and products into a single hub for the entire industry, from building product manufacturers to contractors and specialty trades to architects and engineers. The company''s products include Dodge Global Network, Dodge PlanRoom, Dodge PipeLine, Dodge SpecShare, Dodge BuildShare, Dodge MarketShare, and the Sweets family of products. To learn more, please visit .



Joan Piccariello
Lean Construction Institute
+1 703-387-3046


Benjamin Gorelick
Spector & Associates
+1 212-943-5858

Weitere Infos zu dieser Pressemeldung:

Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:



PresseKontakt / Agentur:



drucken  als PDF  an Freund senden  Powerwave Well Stimulation Project Kicks Off in the Kingdom of Bahrain
Gone but not forgotten: a candlelight memorial for the city''s homeless
Bereitgestellt von Benutzer: Marketwired
Datum: 21.12.2016 - 11:01 Uhr
Sprache: Deutsch
News-ID 1477156
Anzahl Zeichen: 2492

contact information:
Contact person:
Town:

ARLINGTON, VA


Phone:

Kategorie:

Non Profits


Typ of Press Release:
type of sending:
Date of sending:
Anmerkungen:


Diese Pressemitteilung wurde bisher 525 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Lean projects are three times more likely to complete ahead of schedule according to Dodge Data & Analytics'' research
"
steht unter der journalistisch-redaktionellen Verantwortung von

Lean Construction Institute (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Lean Construction Institute



 

Who is online

All members: 10 562
Register today: 1
Register yesterday: 2
Members online: 0
Guests online: 74


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.