Argonaut Gold Announces Q3 Production of 26,322 Gold Equivalent Ounces and Revised Guidance

ID: 1463925

(firmenpresse) - TORONTO, ONTARIO -- (Marketwired) -- 10/17/16 -- Argonaut Gold Inc. (TSX: AR) ("Argonaut", "Argonaut Gold" or the "Company") reports production of 26,322 gold equivalent ounces ("GEOs") during the third quarter ended September 30, 2016 ("Q3"). The lower than anticipated production during the third quarter is primarily a result of two factors at the Company''s El Castillo mine: higher than anticipated rainfall and changes in mine sequencing. Given the lower than planned production, the Company is adjusting its 2016 production guidance to between 115,000 and 120,000 GEOs (previously 130,000 to 135,000 GEOs). All dollars in this press release are expressed in U.S. dollars, unless otherwise noted.

During Q3, the Company produced 13,161 GEOs at its El Castillo mine and 13,161 GEOs at its La Colorada mine for a total of 26,322 GEOs.

At El Castillo, production at the operation was negatively affected by heavy rainfall during the period, which hampered both mining and crusher throughput. Unusually heavy rainfall during Q3 amounted to 344.5 millimetres versus 132.0 millimetres during the same period in 2015. In addition, the Company estimates that during 2016 it will have mined approximately 2.8 million tonnes of ore at an average grade of 0.23 grams gold per tonne that was not in the original 2016 mine plan. This ore is comprised of lower grade oxide, transition and higher grade sulphide material. While economic, the sulphide ore yields significantly lower recoveries. The additional ore tonnes have impacted mine sequencing which has delayed mining the higher grade oxide ore phases of the pit that had been planned to be mined during 2016 and therefore lowered production. This change will have a positive impact on 2017 production, as the Company originally had no oxide ore scheduled to be mined during 2017 in the life of mine plan ("LOM plan") (see Annual Information Form filed March 16, 2016 on ) but now anticipates mining approximately 60% oxide ore during 2017. Also during Q3, the CR2 crushing unit, relocated from La Colorada to El Castillo during August 2016, completed its ramp up to over 5,000 tonnes per day. This additional crushing should positively impact production during the fourth quarter 2016 and 2017 compared to the LOM plan.





At La Colorada, the Company continues to encounter more economic mineralized material than anticipated. While the Company is pleased to discover areas of economic low grade material, processing this material contributed to lower gold production compared to the planned processing of higher grade material during 2016. These low grade gains were partially offset by higher than budgeted throughput and a reduced stripping ratio.

Pete Dougherty, President and CEO, stated: "Heavy rainfall during the quarter at El Castillo made it extremely difficult to hit our mining and throughput targets. Also at El Castillo, due to the revision of mine sequencing, we have mined much lower grade oxide and much more sulphide ore than planned in 2016 which will lead to more oxide production in 2017. Now that the rainy season is past us, we are mining the higher grade oxide ore from phase six. We believe that the fourth quarter should improve in terms of ore placements -- particularly with the additional crushing capacity.

"At La Colorada, it is important to note that we have not changed our cutoff grades. Much of what was classified as waste in our mine model turned out to be above our cutoff grade and is now considered economic. This positive development increases our tonnages, lowers the strip ratio and extends mine life. Additionally, the recent drilling at the El Creston deposit showed encouraging results as we begin preparing this pit for production."

THIRD QUARTER 2016 AND RECENT HIGHLIGHTS:

Corporate Highlights

El Castillo

La Colorada

San Antonio

Argonaut Gold Q3 Financial Results Conference Call and Webcast:

The Company anticipates releasing results after the close of market on November 3, 2016 and will host the Q3 financial results call on November 4, 2016 at 8:30 am EDT.

The conference call replay will be available from 11:30 am EDT on November 4, 2016 until 11:59 pm EST on November 18, 2016.

About Argonaut Gold

Argonaut Gold is a Canadian gold company engaged in exploration, mine development and production activities. Its primary assets are the production stage El Castillo mine in Durango, Mexico and La Colorada mine in Sonora, Mexico. Advanced exploration stage projects include the San Antonio project in Baja California Sur, Mexico, the Magino project in Ontario, Canada and the San Agustin project in Durango, Mexico. The Company also has several exploration stage projects, all of which are located in North America.

Cautionary Note Regarding Forward-looking Statements

This press release contains certain "forward-looking statements" and "forward-looking information" under applicable Canadian securities laws concerning the proposed transaction and the business, operations and financial performance and condition of Argonaut Gold Inc. ("Argonaut" or "Argonaut Gold"). Forward-looking statements and forward-looking information include, but are not limited to, statements with respect to estimated production and mine life of the various mineral projects of Argonaut; synergies and financial impact of completed acquisitions; the benefits of the development potential of the properties of Argonaut; the future price of gold, copper, and silver; the estimation of mineral reserves and resources; the realization of mineral reserve estimates; the timing and amount of estimated future production; costs of production; success of exploration activities; and currency exchange rate fluctuations. Except for statements of historical fact relating to Argonaut, certain information contained herein constitutes forward-looking statements. Forward-looking statements are frequently characterized by words such as "plan," "expect," "project," "intend," "believe," "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are based on a number of assumptions and subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. Many of these assumptions are based on factors and events that are not within the control of Argonaut and there is no assurance they will prove to be correct.

Factors that could cause actual results to vary materially from results anticipated by such forward-looking statements include changes in market conditions, variations in ore grade or recovery rates, risks relating to international operations, fluctuating metal prices and currency exchange rates, changes in project parameters, the possibility of project cost overruns or unanticipated costs and expenses, labour disputes and other risks of the mining industry, failure of plant, equipment or processes to operate as anticipated. Although Argonaut has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Argonaut undertakes no obligation to update forward-looking statements if circumstances or management''s estimates or opinions should change except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking statements to the extent they involve estimates of the mineralization that will be encountered if the property is developed. Comparative market information is as of a date prior to the date of this document.

Qualified Person, Technical Information and Mineral Properties Reports

Technical information included in this release was supervised and approved by Thomas Burkhart, Argonaut Gold''s Vice President of Exploration, and a Qualified Person under NI 43-101. For further information on the Company''s material properties, please see the reports as listed below on the Company''s website or on :

Mineral resources referenced herein are not mineral reserves and do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. The mineral resource estimates may include inferred mineral resources that are normally considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

The Company cautions that a PEA is preliminary in nature and that it relies upon mineral resource estimates which have the considerations noted above applied to them. There is no certainty that a PEA will be realized or that any of the resources will ever be upgraded to reserves.



Contacts:
Argonaut Gold Inc.
Dan Symons
Vice President, Investor Relations
416-915-3107

Weitere Infos zu dieser Pressemeldung:

Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:



PresseKontakt / Agentur:



drucken  als PDF  an Freund senden  Geomega Appoints New Chief Financial Officer
Eloro Resources'' Acquisition of a 100% Interest in the La Victoria Gold/Silver Property Closes in Escrow
Bereitgestellt von Benutzer: Marketwired
Datum: 17.10.2016 - 05:00 Uhr
Sprache: Deutsch
News-ID 1463925
Anzahl Zeichen: 3781

contact information:
Contact person:
Town:

TORONTO, ONTARIO


Phone:

Kategorie:

Mining & Metals


Typ of Press Release:
type of sending:
Date of sending:
Anmerkungen:


Diese Pressemitteilung wurde bisher 150 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Argonaut Gold Announces Q3 Production of 26,322 Gold Equivalent Ounces and Revised Guidance
"
steht unter der journalistisch-redaktionellen Verantwortung von

Argonaut Gold Inc. (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Argonaut Gold Inc.



 

Who is online

All members: 10 677
Register today: 1
Register yesterday: 0
Members online: 0
Guests online: 169


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.