businesspress24.com - Silver Bear Announces Positive Updated Mine Plan and Feasibility Study at the Mangazeisky Silver Pro
 

Silver Bear Announces Positive Updated Mine Plan and Feasibility Study at the Mangazeisky Silver Project, Yakutia, Russia

ID: 1461793

(firmenpresse) - TORONTO, ONTARIO -- (Marketwired) -- 10/04/16 -- Silver Bear Resources Inc. ("Silver Bear" or the "Company") (TSX: SBR) is pleased to announce a 66% increase in pre-tax NPV to US$132.6 million for the Vertikalny Central deposit of its Mangazeisky Silver Project (the "Project") in the Republic of Sakha (Yakutia), Russia following the results of an updated National Instrument 43-101 ("NI 43-101") feasibility study (the Updated Feasibility Study"). The NI 43-101 Updated Feasibility Study will be filed on SEDAR within 45 days of this release.

Graham Hill, President and Chief Executive Officer, commented: "The Updated Feasibility Study demonstrates that we are able to realise the increased value in the recently updated Vertikalny mineral resource estimate, and highlights our project''s extremely robust economics. The better defined and even higher grade ore zones have allowed us to refine the open pit and underground designs to maximise operating cash flow, particularly in the first half of the mine life. The outcome of this effort is reflected in a 97% increase in pre-tax IRR from 43.6% to 86.1% and the pre-tax NPV (5%) from US$ 79.7 million to US$ 132.6 million, with only a nominal increase in initial capital costs.

The updated mine plan requires no change to the process facility design and associated infrastructure and we continue to drive construction to start commissioning by the end of 2016. During this month, the process plant weather-shield and mill foundations were completed allowing us to continue construction and installation of mechanical and electrical equipment during the remainder of the year. We anticipate starting commissioning work on the boiler heating system for the process plant building and the main power generating plant during October. In addition, we have started the mechanical erection of the ball mill and plan to complete that work by the end of October."

Updated Feasibility Study Highlights

Project Execution





The Company is on track to commence steady state production starting in Q1 2017. A licensed Russian design institute (EMC Mining LLC ("EMC") in St Petersburg) continues to provide engineering services for the processing facility and associated mine site infrastructure. Note that the Updated Feasibility Study showed that no change is required to the process design as a result of the updated geology and mine plan. The Company has proceeded with construction in advance of regulatory approval for the project and expects that all of the permits needed for construction and operation will be in place prior to the start of production. The Company will commence production only once all necessary permits and approvals are in place.

Major infrastructure such as the buildings to provide shelter during mechanical and electrical installation have been erected and mechanical and electrical installation can start in October 2016.

More detailed Updated Feasibility Study results can be found in Appendix A The Updated Feasibility Study consultants were led by Tetra Tech WEI Inc. ("Tetra Tech") and comprised an independent, multidisciplinary team including SRK Consulting (UK) Limited ("SRK") and Environmental Resource Management Consultants Inc. ("ERM").

Filing of Technical Report - Vertikalny Mineral Resource Update

The Company is also pleased to announce that on September 21, 2016 it filed the NI 43-101 Technical Report ("Technical Report") for the mineral resource estimate update of its Vertikalny deposits, located within its wholly-owned Mangazeisky Project. Tetra Tech prepared the Technical Report and it supports the Company''s announcement of August 8, 2016.

To view and download the Technical Report, please visit under the Company''s profile. The report will also be available on the Company''s website at .

About Silver Bear

Silver Bear (TSX: SBR) is focused on the development of its wholly-owned Mangazeisky Silver Project, covering a licence area of approximately 570 km2 that includes the high-grade Vertikalny deposit (amongst the highest grade silver deposits in the world), located 400 km north of Yakutsk in the Republic of Sakha within the Russian Federation. The Company was granted a 20-year mining licence for the Vertikalny deposit in September 2013 and recently updated its Feasibility Study in Q4 2016. Other information relating to Silver Bear is available on SEDAR at as well as on the Company''s website at .

Cautionary Notes

This release and subsequent oral statements made by and on behalf of the Company may contain forward-looking statements, which reflect management''s expectations. Wherever possible, words such as "intends", "expects", "scheduled", "estimates", "anticipates", "believes" and similar expressions or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, have been used to identify these forward-looking statements. Although the forward-looking statements contained in this release reflect management''s current beliefs based upon information currently available to management and based upon what management believes to be reasonable assumptions, Silver Bear cannot be certain that actual results will be consistent with these forward-looking statements. A number of factors could cause events and achievements to differ materially from the results expressed or implied in the forward-looking statements. Such risk factors include but are not limited to risk factors identified by Silver Bear in its continuous disclosure filings filed from time to time on SEDAR. These factors should be considered carefully and prospective investors should not place undue reliance on the forward-looking statements. Forward-looking statements necessarily involve significant known and unknown risks, assumptions and uncertainties that may cause Silver Bear''s actual results, events, prospects and opportunities to differ materially from those expressed or implied by such forward-looking statements. Although Silver Bear has attempted to identify important risks and factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors and risks that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, prospective investors should not place undue reliance on forward-looking statements. These forward-looking statements are made as of the date of this release, and Silver Bear assumes no obligation to update or revise them to reflect new events or circumstances, unless otherwise required by law.

Geology & Mineral Resource

The Vertikalny Central deposit is a steeply dipping structurally controlled epithermal vein system that cross cuts the sedimentary host rocks. The mineralisation is expressed as breccias comprising siderite-sphalerite-galena and silver sulphosalts. Mineralisation is usually associated with the presence of vertical dykes of intermediate to basic composition.

At Vertikalny Central a total of 256 holes have been drilled and 65 trenches excavated over a strike length of 2 km since 2007. In total, 37,130 m have been drilled, and trench excavations extend to 2,180 m.

Mineral Resources for a series of satellite deposits included in the Property are summarised in Table 1 below. The satellite deposits include Vertikalny Northwest located 1 km to the north of Vertikalny Central, Nizhny Endybal situated approximately 2.5 km east of Vertikalny Central, and the Mangazeisky North deposits located 7 km to the north of Vertikalny Central.

Table 2 provides a summary of all of the Current Mineral Resources within the Mangazeisky property.

Notes:

The effective date of the original Nizhny Endybal Resource estimate was 11th of September 2012, this resource was re-stated with a higher cut-off grade on the 10th of June 2015. The effective date of the Mangazeisky South resource is 10th of June 2015. The effective date of the Mangazeisky North Resource is 31st of March 2016. The effective date of the Vertikalny Central Resource estimate was 8th July 2016.Mineral Resource estimation parameters:

Mineral Resources that are not Mineral Reserves to not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political marketing, or other relevant issues. Although Silver Bear and Tetra Tech are not aware of any material barrier to eventual economic extraction.

Mineral Reserve

The ore body will be extracted in an open pit, followed by underground mine. The open pit (the first four years of production) will consist of a conventional drill, blast, load, and haul operation, using the current fleet on site, supplemented with leased equipment. Most of the capital for the open pit will only be limited to trucks, lighting units, pumps, site office facility, and light vehicles. The open pit consists of the North and South pits that are sequenced in the mining schedule. The open pit design is optimised to integrate the underground portal designs where needed. A 30% mining dilution and 95% mining recovery was applied to the scheduled tonnes and grades.

As Vertikalny is a steeply dipping ore body in the range of 60 to 90 degrees with orebody thicknesses (below the designed open pit perimeters) ranging between 0.5 and 4m, mechanized sub level open stoping was selected as the underground mining method. Two distinct underground areas in the north and the south will be developed. The Northern section, which contains the higher ore grades, will be exploited first via a decline from the top bench of the open pit. The southern section will be accessed through a number of ore drive portals, developed from within the South pit and linked together with a decline system; providing access to the deeper stoping areas.

The underground mineable areas was optimised using Datamine''s MSO software. An MSO cut-off of 300g/t diluted Ag (approximately 450g/t in-situ cut-off in stope shapes) was considered for the final mine design with typical stope dimensions of 25m height, 20m wide and average stope widths of around 1.85m. Stopes located near the crown pillars assumed a 5% mining loss and a further 10% unforeseen ore extraction loss whilst the average stopes assumed a 5% mining loss and a further 5% unforeseen ore extraction loss. The stope designs also considered the appropriate hydraulic radius recommendations and in-situ pillars were left in the lower grade areas where plausible. Dilution was modelled for each stope: the calculated minimum overbreak were 0.25 m on each side which equates to 0.5 m total. This resulted in a dilution range of 15% to 38% with an average of 30% which, along with the assumed 95% mining recovery, is in accordance with Russian standard practice. The open pit and underground cut-off grades are 250 g/t and 450 g/t, respectively. The Mineral Reserve statement is as of September 23rd, 2016 and is shown in Table 3.

Processing

The feasibility study process plant design is based on 110,000 t/a capacity, with a LOM average silver grade of 772 g/t, and is expected to provide an average silver recovery from oxide ore of 85.0%. The average silver recovery of the primary ore (a small portion of the plant feed scheduled at the end of mine life) is expected to be 69.7%.

The process flowsheet consists of a standard crushing and grinding circuit, followed by gravity concentration and cyanide tank leach of the gravity tails. The gravity concentrates will be processed by intensive cyanidation. The leached slurry from the tank leach and intensive cyanidation will go through a simple counter current decantation washing system and the pregnant solution will be processed by direct electrowinning to recover silver metal in powder form with a purity exceeding 99.9% Ag.

Tailings

The tailings management facility ("TMF") will consist of a dry stack facility, contained within a fully-lined pad, surrounded by a series of containment bunds. A clarification pond to store all process affected fluids before retreatment is included in the design. The TMF will be constructed 0.2 km northeast of the plant site, and will cover an area of 7.69 ha. Approximately 0.8 Mt of tailings material will require storage over the 8-year LOM.

Capital and Operating Costs

The total estimated initial capital cost for the design, construction, installation, and commissioning of all facilities and equipment is $50.4 million (Table 4).

The LOM operating cost estimate for the Project consists of mining, processing, and G&A costs (which includes TMF and site water management costs) and is estimated at $154.38/t processed (Table 5).

Tetra Tech investigated the sensitivity of NPV and IRR to the key project variables of silver price, exchange rate, capital costs and operating costs.

Sensitivities

The Project''s pre-tax NPV, calculated at a 5% discount rate, is most sensitive to silver price followed by exchange rate, on-site operating costs, and capital costs, as shown in Figure 1.

Figure 1 Pre-tax NPV Sensitivity Analysis:

The Project''s pre-tax IRR is most sensitive to silver price followed by exchange rate, capital costs, and on-site operating costs (Figure 2).

Figure 2 Pre-tax IRR Sensitivity Analysis:

Approval Process

The Company has completed the Russian design documentation required for the State review in Q3 2016. Following regulatory review and approval of the project, which the Company estimates could be granted in Q4 2016, the Company will be in a position to apply for a Permit for Construction, followed by the balance of construction and operating permits shortly thereafter.

The Company acknowledges that there is a risk associated with undertaking construction in advance of obtaining the necessary regulatory approvals. It is possible that the regulatory approvals process may result in production delays and /or mandated design changes that may lead to modification of constructed site components. To mitigate the impact and likelihood of these risks, the approvals process is being managed by dedicated teams in Yakutsk and St Petersburg. The Company has also engaged an experienced, licensed Russian institute, EMC, to complete the design and assist with the submission and defence of the design documentation, as well as assist with permit applications. The Company is of the view that this risk caused by regulatory non-conformance is outweighed by the opportunity to maintain project momentum and investor interest, both essential for the successful completion of the project, as well as the earliest production of silver.





Contacts:
Silver Bear Resources Inc.
Graham Hill
President and Chief Executive Officer
+7 916 731 5673


Silver Bear Resources Inc.
Judith Webster
Investor Relations Manager & Corporate Secretary
+416 453 8818


Buchanan UK
Bobby Morse
+44 (0) 20 7466 5000

Buchanan UK
Anna Michniewicz
+44 (0) 20 7466 5146

Weitere Infos zu dieser Pressemeldung:

Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:



PresseKontakt / Agentur:



drucken  als PDF  an Freund senden  Red Pine Exploration Finds Additional Gold in the Sampled Historic Holes of Its Wawa Gold Project; New Results Include 128.56 Metres @ 0.94 g/t Gold
NuLegacy Arranges 20 Million C$0.45/Unit Financing
Bereitgestellt von Benutzer: Marketwired
Datum: 04.10.2016 - 04:00 Uhr
Sprache: Deutsch
News-ID 1461793
Anzahl Zeichen: 2787

contact information:
Contact person:
Town:

TORONTO, ONTARIO


Phone:

Kategorie:

Mining & Metals


Typ of Press Release:
type of sending:
Date of sending:
Anmerkungen:


Diese Pressemitteilung wurde bisher 189 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Silver Bear Announces Positive Updated Mine Plan and Feasibility Study at the Mangazeisky Silver Project, Yakutia, Russia
"
steht unter der journalistisch-redaktionellen Verantwortung von

Silver Bear Resources Inc. (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Silver Bear Resources Inc.



 

Who is online

All members: 10 677
Register today: 1
Register yesterday: 0
Members online: 0
Guests online: 264


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.