businesspress24.com - Closure of Water Treatment Plant Latest Setback For Tulsequah Chief Mine Proposal
 

Closure of Water Treatment Plant Latest Setback For Tulsequah Chief Mine Proposal

ID: 1128449

Chieftain Metals Faces Rising Costs; Financing, Permitting and Access Problems Non-Compliance with Permit and Cleanup Orders Threatens Water Quality and Salmon

(firmenpresse) - JUNEAU, ALASKA -- (Marketwire) -- 06/27/12 -- Chieftain Metals announced on June 6 its intent to close the Interim Water Treatment Plant installed at the Tulsequah Chief site in November 2011 to address chronic acid mine drainage and heavy metals pollution. The company will now be violating its discharge permit.

"Chieftain's halt to pollution control is another broken promise and more evidence this mine is simply not viable from an economic, environmental or logistical perspective," said Chris Zimmer of Rivers Without Borders. "Closure of the water treatment plant is a failure by Chieftain to meet its legally mandated environmental responsibilities, threatens water quality and wild salmon in the Taku, and demonstrates Chieftain has been unable to interest investors in the mine."

Chieftain's June 6 letter to Environment Canada references increasing costs, "significant" safety concerns, unanticipated technical challenges, and the need for Chieftain to undertake a "comprehensive review" of the project's design, economics and construction processes. This letter comes on the heels of other setbacks for the company, including:

"The inability of Chieftain, and its predecessor Redfern, to develop this mine and its history of environmental, financial and technical problems clearly demonstrates the mine simply is not viable. Chieftain says it needs more time to fix the problems and obtain financing. But more time won't help; the Tulsequah Chief is simply a bad idea," said Zimmer.

The Tulsequah Chief proposal has created controversy since Redfern Resources announced plans to develop it in the early 1990s. Downstream stakeholders such as Alaskan fishermen, Alaska state agencies and legislators, and US federal agencies have expressed major concerns about threats to water quality and wild salmon. The Taku River Tlingit First Nation and Atlin residents have strong concerns related to the access road. The project has also suffered from financial problems such as bankruptcies, overly optimistic financial analysis and predictions, increasing costs and a lack of investors.





The project was originally owned by Cominco which abandoned the operation in the 1950s without conducting any site remediation. Redfern bought the Tulsequah Chief site and announced development plans in the early 1990s. Despite numerous cleanup orders, Redfern did little to address the pollution problem, characterized as "acutely lethal" by Environment Canada. Acid mine drainage and heavy metals continued flowing into the Tulsequah and Taku Rivers unabated. Redfern declared bankruptcy in March 2009. Chieftain Metals was incorporated in November 2009 to buy the project out of the bankruptcy and purchased the Tulsequah Chief site in September 2010. In November 2011, Chieftain installed an Interim Water Treatment Plant to treat the pollution but the plant has not worked as expected.

"We are now back to the situation of pollution flowing into the river and the mining company unable to clean it up. Chieftain says mine development is a long-term solution to the pollution problem, but cleaning up mine pollution by initiating more mining makes no sense. Cooperative work between governments is now needed to permanently address the pollution problems," said Zimmer.

For more information, including a copy of Chieftain Metals' June 6 letter, see



Contacts:
Rivers Without Borders
Chris Zimmer
(907) 586-2166


Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:



PresseKontakt / Agentur:



drucken  als PDF  an Freund senden  Semcan Inc. Announces Randy Fowlie Will Not Be Standing for Re-Election to the Board of Directors
HaiCo Acquires Tree Farm Licence 60 & New Financing for Haida Tourism
Bereitgestellt von Benutzer: MARKETWIRE
Datum: 27.06.2012 - 09:00 Uhr
Sprache: Deutsch
News-ID 1128449
Anzahl Zeichen: 0

contact information:
Contact person:
Town:

JUNEAU, ALASKA


Phone:

Kategorie:

Natural Resource Management


Anmerkungen:


Diese Pressemitteilung wurde bisher 140 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Closure of Water Treatment Plant Latest Setback For Tulsequah Chief Mine Proposal
"
steht unter der journalistisch-redaktionellen Verantwortung von

Rivers Without Borders (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Rivers Without Borders



 

Who is online

All members: 10 563
Register today: 0
Register yesterday: 0
Members online: 1
Guests online: 103


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.