Bruce Power: Update on Unit 2 Return to Operations

ID: 1094539

(firmenpresse) - TIVERTON, ONTARIO -- (Marketwire) -- 03/20/12 -- Earlier this morning, Bruce Power's operations team removed reactor shutdown guarantees on Unit 2 following completion of minor repairs to a pump system.

As previously reported, following CNSC approval on Friday, which allowed Bruce Power to remove shutdown guarantees on Unit 2, the company's operations team detected a leak on a Unit 2 pump system during restart activities. Bruce Power took appropriate actions to safely and quickly isolate the leak as per the company's operating procedures.

There was no impact on the rest of Bruce A, the public, external environment or worker safety.

The company will continue with the return to operations program on both Units 1 and 2, which will involve the powering-up and commissioning of many complex systems in preparation to provide 1,500 megawatts of additional electricity for the province.

About Bruce Power

Bruce Power is a partnership among Cameco Corporation, TransCanada Corporation, BPC Generation Infrastructure Trust, a trust established by the Ontario Municipal Employees Retirement System, the Power Workers' Union and The Society of Energy Professionals.



Contacts:
Bruce Power
John Peevers
519-361-6583


Bruce Power
24-hour Duty Media Officer
519-361-6161




Themen in dieser Pressemitteilung:


Unternehmensinformation / Kurzprofil:



Leseranfragen:



PresseKontakt / Agentur:



drucken  als PDF  an Freund senden  Covanta Announces Internal Management Changes
Vanuatu Selects WPCS for Renewable Energy Project
Bereitgestellt von Benutzer: MARKETWIRE
Datum: 20.03.2012 - 08:17 Uhr
Sprache: Deutsch
News-ID 1094539
Anzahl Zeichen: 0

contact information:
Contact person:
Town:

TIVERTON, ONTARIO


Phone:

Kategorie:

Alternative Energy


Anmerkungen:


Diese Pressemitteilung wurde bisher 55 mal aufgerufen.


Die Pressemitteilung mit dem Titel:
"Bruce Power: Update on Unit 2 Return to Operations
"
steht unter der journalistisch-redaktionellen Verantwortung von

Bruce Power (Nachricht senden)

Beachten Sie bitte die weiteren Informationen zum Haftungsauschluß (gemäß TMG - TeleMedianGesetz) und dem Datenschutz (gemäß der DSGVO).


Alle Meldungen von Bruce Power



 

Who is online

All members: 10 667
Register today: 0
Register yesterday: 0
Members online: 0
Guests online: 934


Don't have an account yet? You can create one. As registered user you have some advantages like theme manager, comments configuration and post comments with your name.